Projects
Asset-native delivery — every project linked to assets, finance, and outcomes.
Active Projects
5
In Delivery
3
At Risk
2
Total Budget
A$20,660,000
Spend to Date
A$1,360,000
Portfolio Heatmap
Schedule (SPI) × Cost (CPI) performance — circle size = budget
Behind & OverOver BudgetBehind ScheduleOn Track
DL-01 boom refurbishment and major shutdown
SPI 1.00 · CPI 3.07
CV-02 overland belt replacement
SPI 1.00 · CPI 1.00
CHPP yield recovery programme
SPI 1.00 · CPI 1.55
Spontaneous combustion management upgrade
SPI 1.00 · CPI 1.52
Haul fleet tyre life improvement
SPI 1.33 · CPI 1.29
← Behind scheduleSchedule Performance (SPI)Ahead of schedule →
Planning
(2)In Delivery
(3)BEN-P-103
CHPP yield recovery programme
High
Bengalla Mine (Hunter Valley)
Progress40%
Budget
A$1,200,000
-4.2% vs fcst
Target
Dec 2026
In Delivery
BEN-P-104
Spontaneous combustion management upgrade
High
Bengalla Mine (Hunter Valley)
Progress35%
Budget
A$260,000
-3.8% vs fcst
Target
Dec 2026
In Delivery
BEN-P-105
Haul fleet tyre life improvement
Medium
Bengalla Mine (Hunter Valley)
Progress45%
Budget
A$400,000
-2.5% vs fcst
Target
Feb 2027
In Delivery
Complete