Supply Chain Lead-Time Risk

Not how much stock is held, but whether it arrives before it is needed — cover measured against the lead time a supplier actually delivers to, and against change-outs that are already due inside their own procurement window.

How the site filter works

Your site choice is remembered across workspace views.

Site filtering uses recorded compatible equipment types, not storage-bin names. Matching parts are candidate shared supply, not confirmed fitment or stock allocated to this site; quantities, usage, costs and lead times retain their full-register basis. Parts without compatibility links remain under All locations. Verify fitment, stock ownership and transfer time before ordering.

29 of 29 loaded parts (limit 300); 31 of 31 fleet units (limit 300). Up to 200 supplier records inform the existing risk model. Component and failure-window calculations follow selected-site assets; decision deduplication retains all loaded decisions.

Parts exposed to lead time

7

Worst gap 153 days with no shelf cover

Order today

7

Cover already inside the lead time

Change-outs already late

5

7 components due within 90 days

Committed spend, 90 days

A$4.2M

Known change-outs, not a forecast

793F C175-16 engine (exchange)

793F-ENG-C175 · Westrac (Caterpillar) (DEMO) · critical criticality

Order nowCritical

On hand

0

Effective lead time

153d vs 140d quoted

Exposure

153d uncovered

Order by

Today

0d stock cover153d to resupply

Out of stock with a 153-day replenishment — any demand now becomes 153 days of downtime. Westrac (Caterpillar) (DEMO) delivers on time 91% of the time, so the quoted lead time is not the planning lead time.

DMC 1000 apex and vortex finder set

DMC-APEX-1000 · Multotec Australia (DEMO) · critical criticality

Order nowCritical

On hand

0

Effective lead time

31d vs 28d quoted

Exposure

31d uncovered

Order by

Today

0d stock cover31d to resupply

0 days of cover against a 31-day lead time — a 31-day gap with nothing on the shelf. Multotec Australia (DEMO) delivers on time 90% of the time, so the quoted lead time is not the planning lead time.

Dragline hoist motor (rotable)

DL-MTR-HOIST-ROT · Hunter Valley Electrical Services (DEMO) · critical criticality

Order nowCritical

On hand

0

Effective lead time

64d vs 60d quoted

Exposure

64d uncovered

Order by

Today

0d stock cover64d to resupply

Out of stock with a 64-day replenishment — any demand now becomes 64 days of downtime. Hunter Valley Electrical Services (DEMO) delivers on time 94% of the time, so the quoted lead time is not the planning lead time.

Dragline hoist rope 83 mm (pair)

DL-ROPE-HOIST-83 · Bridon-Bekaert Ropes Group (DEMO) · critical criticality

Order nowCritical

On hand

0

Effective lead time

22d vs 21d quoted

Exposure

22d uncovered

Order by

Today

0d stock cover22d to resupply

0 days of cover against a 22-day lead time — a 22-day gap with nothing on the shelf. Bridon-Bekaert Ropes Group (DEMO) delivers on time 93% of the time, so the quoted lead time is not the planning lead time.

Screen exciter (rotable)

SCR-EXCITER · Schenck Process Australia (DEMO) · critical criticality

Order nowCritical

On hand

0

Effective lead time

41d vs 35d quoted

Exposure

41d uncovered

Order by

Today

0d stock cover41d to resupply

0 days of cover against a 41-day lead time — a 41-day gap with nothing on the shelf. Schenck Process Australia (DEMO) delivers on time 84% of the time, so the quoted lead time is not the planning lead time.

Sizer gearbox exchange unit

SZ-GBX-625 · MMD Australia (DEMO) · critical criticality

Order nowCritical

On hand

0

Effective lead time

103d vs 90d quoted

Exposure

103d uncovered

Order by

Today

0d stock cover103d to resupply

Out of stock with a 103-day replenishment — any demand now becomes 103 days of downtime. MMD Australia (DEMO) delivers on time 85% of the time, so the quoted lead time is not the planning lead time.

Centrifuge basket H1000

CF-BASKET-H1000 · Schenck Process Australia (DEMO) · high criticality

Order nowCritical

On hand

0

Effective lead time

81d vs 70d quoted

Exposure

81d uncovered

Order by

Today

0d stock cover81d to resupply

Out of stock with a 81-day replenishment — any demand now becomes 81 days of downtime. Schenck Process Australia (DEMO) delivers on time 84% of the time, so the quoted lead time is not the planning lead time.

OTR tyre 59/80R63 (793F)

TYRE-59-80R63 · Bridgestone Mining Solutions (DEMO) · critical criticality

Watch

On hand

10

Effective lead time

53d vs 45d quoted

Exposure

None

Order by

2026-11-09

66d stock cover53d to resupply

Covered — reorder by 2026-11-09 to stay ahead of the lead time. Bridgestone Mining Solutions (DEMO) delivers on time 82% of the time, so the quoted lead time is not the planning lead time.

OTR tyre 53/80R63 (830E)

TYRE-53-80R63 · Bridgestone Mining Solutions (DEMO) · high criticality

Watch

On hand

5

Effective lead time

53d vs 45d quoted

Exposure

None

Order by

2026-11-11

68d stock cover53d to resupply

Covered — reorder by 2026-11-11 to stay ahead of the lead time. Bridgestone Mining Solutions (DEMO) delivers on time 82% of the time, so the quoted lead time is not the planning lead time.

Dragline bucket tooth set (ESCO)

DL-GET-TOOTH-SET · ESCO (Weir) (DEMO) · critical criticality

Covered

On hand

2

Effective lead time

7d

Exposure

None

Order by

2026-11-24

35d stock cover7d to resupply

Covered — reorder by 2026-11-24 to stay ahead of the lead time.

Dragline drag rope 89 mm

DL-ROPE-DRAG-89 · Bridon-Bekaert Ropes Group (DEMO) · critical criticality

Covered

On hand

1

Effective lead time

22d vs 21d quoted

Exposure

None

Order by

2027-01-13

100d stock cover22d to resupply

Covered — reorder by 2027-01-13 to stay ahead of the lead time. Bridon-Bekaert Ropes Group (DEMO) delivers on time 93% of the time, so the quoted lead time is not the planning lead time.

Dragline trailing cable 3.3 kV (per 300 m)

HV-CABLE-TRAIL · Hunter Valley Electrical Services (DEMO) · critical criticality

Covered

On hand

1

Effective lead time

59d vs 56d quoted

Exposure

None

Order by

2027-11-01

429d stock cover59d to resupply

Covered — reorder by 2027-11-01 to stay ahead of the lead time. Hunter Valley Electrical Services (DEMO) delivers on time 94% of the time, so the quoted lead time is not the planning lead time.

Steel-cord belt ST2500 1400 mm (per 300 m roll)

BELT-ST2500-1400 · Fenner Dunlop Australia (DEMO) · critical criticality

Covered

On hand

2

Effective lead time

171d vs 150d quoted

Exposure

None

Order by

2028-03-06

667d stock cover171d to resupply

Covered — reorder by 2028-03-06 to stay ahead of the lead time. Fenner Dunlop Australia (DEMO) delivers on time 86% of the time, so the quoted lead time is not the planning lead time.

Steel-cord splice kit (hot vulcanised)

SPLICE-KIT-SC · Fenner Dunlop Australia (DEMO) · critical criticality

Covered

On hand

2

Effective lead time

24d vs 21d quoted

Exposure

None

Order by

2026-11-27

55d stock cover24d to resupply

Covered — reorder by 2026-11-27 to stay ahead of the lead time. Fenner Dunlop Australia (DEMO) delivers on time 86% of the time, so the quoted lead time is not the planning lead time.

Warman 14/12 impeller

WRM-1412-IMP · Weir Minerals Australia (DEMO) · critical criticality

Covered

On hand

1

Effective lead time

39d vs 35d quoted

Exposure

None

Order by

2027-01-07

111d stock cover39d to resupply

Covered — reorder by 2027-01-07 to stay ahead of the lead time. Weir Minerals Australia (DEMO) delivers on time 89% of the time, so the quoted lead time is not the planning lead time.

793F final drive (rotable pair)

793F-FD-PAIR · Westrac (Caterpillar) (DEMO) · high criticality

Covered

On hand

1

Effective lead time

98d vs 90d quoted

Exposure

None

Order by

2027-03-28

250d stock cover98d to resupply

Covered — reorder by 2027-03-28 to stay ahead of the lead time. Westrac (Caterpillar) (DEMO) delivers on time 91% of the time, so the quoted lead time is not the planning lead time.

Ceramic pulley lagging (per pulley)

PULLEY-LAG-CER · Fenner Dunlop Australia (DEMO) · high criticality

Covered

On hand

2

Effective lead time

40d vs 35d quoted

Exposure

None

Order by

2027-04-27

222d stock cover40d to resupply

Covered — reorder by 2027-04-27 to stay ahead of the lead time. Fenner Dunlop Australia (DEMO) delivers on time 86% of the time, so the quoted lead time is not the planning lead time.

EX5600 main hydraulic pump set

EX-HYD-PUMP-SET · Komatsu Australia (DEMO) · high criticality

Covered

On hand

1

Effective lead time

68d vs 60d quoted

Exposure

None

Order by

2028-01-02

500d stock cover68d to resupply

Covered — reorder by 2028-01-02 to stay ahead of the lead time. Komatsu Australia (DEMO) delivers on time 87% of the time, so the quoted lead time is not the planning lead time.

Sizer tooth segment set 625

SZ-SEG-625 · MMD Australia (DEMO) · high criticality

Covered

On hand

3

Effective lead time

69d vs 60d quoted

Exposure

None

Order by

2027-02-05

170d stock cover69d to resupply

Covered — reorder by 2027-02-05 to stay ahead of the lead time. MMD Australia (DEMO) delivers on time 85% of the time, so the quoted lead time is not the planning lead time.

Steel-cord belt ST1250 1600 mm (per 300 m roll)

BELT-ST1250-1600 · Fenner Dunlop Australia (DEMO) · high criticality

Covered

On hand

1

Effective lead time

148d vs 130d quoted

Exposure

None

Order by

2027-02-06

250d stock cover148d to resupply

Covered — reorder by 2027-02-06 to stay ahead of the lead time. Fenner Dunlop Australia (DEMO) delivers on time 86% of the time, so the quoted lead time is not the planning lead time.

Turnout crossing nose 1 in 9

TRK-CROSSING-19 · Hunter Valley Electrical Services (DEMO) · high criticality

Covered

On hand

1

Effective lead time

64d vs 60d quoted

Exposure

None

Order by

2030-10-02

1500d stock cover64d to resupply

Covered — reorder by 2030-10-02 to stay ahead of the lead time. Hunter Valley Electrical Services (DEMO) delivers on time 94% of the time, so the quoted lead time is not the planning lead time.

Warman 14/12 liner set

WRM-1412-LINER · Weir Minerals Australia (DEMO) · high criticality

Covered

On hand

1

Effective lead time

39d vs 35d quoted

Exposure

None

Order by

2027-01-07

111d stock cover39d to resupply

Covered — reorder by 2027-01-07 to stay ahead of the lead time. Weir Minerals Australia (DEMO) delivers on time 89% of the time, so the quoted lead time is not the planning lead time.

Warman bearing assembly

WRM-BRG-ASSY · Weir Minerals Australia (DEMO) · high criticality

Covered

On hand

2

Effective lead time

39d vs 35d quoted

Exposure

None

Order by

2027-02-11

146d stock cover39d to resupply

Covered — reorder by 2027-02-11 to stay ahead of the lead time. Weir Minerals Australia (DEMO) delivers on time 89% of the time, so the quoted lead time is not the planning lead time.

793F 500 h filter kit

FLT-KIT-793F · Westrac (Caterpillar) (DEMO) · medium criticality

Covered

On hand

22

Effective lead time

15d vs 14d quoted

Exposure

None

Order by

2026-11-19

38d stock cover15d to resupply

Covered — reorder by 2026-11-19 to stay ahead of the lead time. Westrac (Caterpillar) (DEMO) delivers on time 91% of the time, so the quoted lead time is not the planning lead time.

Flygt 2670 impeller and wear ring

PD-FLYGT-IMP · Hunter Valley Electrical Services (DEMO) · medium criticality

Covered

On hand

1

Effective lead time

22d vs 21d quoted

Exposure

None

Order by

2027-01-24

111d stock cover22d to resupply

Covered — reorder by 2027-01-24 to stay ahead of the lead time. Hunter Valley Electrical Services (DEMO) delivers on time 94% of the time, so the quoted lead time is not the planning lead time.

Gearbox oil and filter kit (B3SH)

GBX-B3SH-OIL · Flender Australia (DEMO) · medium criticality

Covered

On hand

6

Effective lead time

17d vs 14d quoted

Exposure

None

Order by

2027-02-16

129d stock cover17d to resupply

Covered — reorder by 2027-02-16 to stay ahead of the lead time. Flender Australia (DEMO) delivers on time 80% of the time, so the quoted lead time is not the planning lead time.

Polyurethane screen panels (set of 40)

SCR-PANEL-PU · Multotec Australia (DEMO) · medium criticality

Covered

On hand

3

Effective lead time

23d vs 21d quoted

Exposure

None

Order by

2026-12-08

65d stock cover23d to resupply

Covered — reorder by 2026-12-08 to stay ahead of the lead time. Multotec Australia (DEMO) delivers on time 90% of the time, so the quoted lead time is not the planning lead time.

Troughing idler set 152 mm

IDLER-152-TROUGH · Fenner Dunlop Australia (DEMO) · medium criticality

Covered

On hand

64

Effective lead time

32d vs 28d quoted

Exposure

None

Order by

2026-11-11

47d stock cover32d to resupply

Covered — reorder by 2026-11-11 to stay ahead of the lead time. Fenner Dunlop Australia (DEMO) delivers on time 86% of the time, so the quoted lead time is not the planning lead time.

Transformer oil sample kit (DGA)

TX-OIL-DGA · Hunter Valley Electrical Services (DEMO) · low criticality

Covered

On hand

6

Effective lead time

7d

Exposure

None

Order by

2028-08-17

667d stock cover7d to resupply

Covered — reorder by 2028-08-17 to stay ahead of the lead time.